How to Specify Four-Panel Construction on an FIBC Purchase Order

Table of Contents

Minimum Order Quantity (MOQ): 1 pallet (typically 125–250+ bulk bags)

How to Specify Four-Panel Construction on an FIBC Purchase Order

To specify four-panel construction on an FIBC purchase order, do not simply write “four-panel bulk bag.” Clearly identify the body as four-panel construction using four separate side panels and a separately attached bottom, then define the product, bulk density, target payload, Safe Working Load (SWL), safety factor, top, bottom, fabric, coating, seam requirements, liner, lift loops, dimensions, critical tolerances, filling method, discharge method, pallet requirements, printing, packing, and approved specification revision.

Here is a terrible purchase order:

“White four-panel bulk bag. Heavy duty.”

That sounds like a specification.

It isn’t.

What product?

What bulk density?

What payload?

What SWL?

What safety factor?

What top?

What bottom?

Coated or uncoated?

Lined or unlined?

What seams?

What loops?

What filled footprint?

How is it filled?

How is it discharged?

What pallet does it need to fit?

What revision are we ordering?

If those answers exist only in someone’s head, you do not have a controlled FIBC specification.

You have a description.

What Does Four-Panel Construction Mean on an FIBC Purchase Order?

Four-panel construction refers to an FIBC body made from four separate side panels joined along vertical seams.

A separate bottom panel completes the main body.

That differentiates it from other body constructions such as:

U-panel.

Circular.

And baffle or form-stable configurations.

But four-panel only describes the body.

It does not tell the supplier everything needed to manufacture the complete FIBC.

How Should Four-Panel Construction Be Written on a Purchase Order?

A useful starting point is:

Body Construction: Four-Panel FIBC Per Approved Drawing

If additional clarification is needed:

Body Construction: Four Separate Side Panels With Separately Attached Bottom Panel, Per Approved Drawing

Then reference the exact drawing or technical specification.

That is much stronger than:

Four-panel bag.

Why “Four-Panel FIBC” Is Not a Complete Specification

Two four-panel bags can look similar and perform very differently.

One may be:

Open top.

Flat bottom.

Uncoated.

Unlined.

Another may be:

Filling spout top.

Discharge spout bottom.

Coated.

Lined.

They are both four-panel FIBCs.

They are not remotely the same packaging system.

What Information Should Be Included on a Four-Panel FIBC Purchase Order?

At minimum, control these variables:

Specification What to Define
📦 Product Actual material being packaged
⚗️ Bulk density Actual value or approved range
⚖️ Payload Target product weight
🧱 Body Four-panel construction
🔵 Top Open, duffle, filling spout, etc.
⬇️ Bottom Flat, spout, duffle, etc.
⚖️ SWL Required Safe Working Load
🛡️ Safety factor Required intended-use classification
🧵 Fabric Required woven polypropylene construction
💧 Coating Coated or uncoated
🪡 Seams Required seam construction
🛍️ Liner Required liner configuration
🪢 Loops Lift-loop style and dimensions
📐 Dimensions Required empty dimensions
📏 Filled geometry Critical filled dimensions if applicable
🎯 Tolerances Critical dimensional tolerances
🪵 Pallet Required pallet compatibility
⚙️ Filling Actual filling method
🔻 Discharge Actual unloading method
🌫️ Containment Dust/sifting requirements
💦 Moisture Required barrier performance
⚡ Static Electrostatic requirements when applicable
🏷️ Printing Artwork and identification
📦 Packing Empty-bag packing requirements
📄 Revision Approved specification revision

That is a real specification.

Specify the Actual Product First

Before worrying about panels, identify what goes inside.

Is it:

Powder?

Pellets?

Granules?

Plastic resin?

Mineral?

Agricultural material?

Food ingredient?

Chemical product?

Recycling material?

Something bulky or irregular?

The material drives the bag.

Specify Product Bulk Density

Bulk density affects:

Required volume.

Target payload.

Filled height.

Filled footprint.

Fabric requirements.

SWL selection.

Warehouse cube.

Transportation economics.

Do not guess.

Use actual product data whenever possible.

Specify the Target Payload

State how much product should be placed into each FIBC.

The target payload should work with:

Bulk density.

Bag volume.

SWL.

Filled geometry.

Handling.

Pallet.

Transportation.

Do not use:

“Fill it until it looks full.”

Specify Safe Working Load

State the required SWL clearly.

Do not use:

Heavy duty.

Extra heavy duty.

Industrial strength.

Super sack strength.

Those phrases are not substitutes for the rated requirement.

Specify the Safety Factor

Specify the appropriate safety factor or intended-use classification.

And remember:

Safety factor is not extra payload capacity.

Do not exceed the rated SWL simply because the bag has a safety factor.

Specify Four-Panel Body Construction Clearly

State:

Body Construction: Four-Panel

Then reference the approved drawing.

This prevents confusion with:

Circular.

U-panel.

Baffle.

Other body constructions.

Specify Whether Baffles Are Required

Four-panel and baffle are not synonyms.

A standard four-panel FIBC can still bulge after filling.

If internal baffles are required for stronger shape control, state that separately.

For example:

Body Construction: Four-Panel With Internal Baffle / Form-Stable Construction Per Approved Drawing

Do not assume the supplier knows you want both.

Specify the Required Empty Dimensions

Define the appropriate:

Width.

Length.

Height.

And other critical dimensions.

But remember:

Empty dimensions do not necessarily equal filled dimensions.

Specify Critical Filled Dimensions When They Matter

If the FIBC must fit:

A pallet.

Warehouse position.

Truck-loading pattern.

Container-loading pattern.

Equipment clearance.

Then filled dimensions may matter more than empty dimensions.

Document the critical requirements.

Specify the Required Filled Footprint

If pallet fit matters, state the target.

Four-panel construction creates a square or rectangular body concept.

But flexible sidewalls can still expand.

Do not assume.

Specify Acceptable Pallet Overhang

If overhang is a problem, quantify the acceptable condition.

“Must fit pallet better” is not a technical requirement.

Specify Realistic Tolerances

Do not apply extremely tight tolerances to every dimension simply because you can.

FIBCs are flexible packaging.

Identify which dimensions affect:

Equipment.

Pallet fit.

Filling.

Discharge.

Handling.

Logistics.

Control those.

Call or Text us at 832.400.1394

Specify the Top Construction Separately

Four-panel describes the body.

Not the top.

State exactly how the FIBC should be filled.

How to Specify Open Top on a Four-Panel FIBC Purchase Order

A straightforward description might be:

Body Construction: Four-Panel

Top Construction: Full Open Top

This can work when broad filling access is required.

How to Specify Duffle Top on a Four-Panel FIBC Purchase Order

Specify:

Body Construction: Four-Panel

Top Construction: Duffle Top With Approved Closure

Then define any critical dimensions and closure requirements.

How to Specify Filling Spout Top on a Four-Panel FIBC Purchase Order

State:

Body Construction: Four-Panel

Top Construction: Filling Spout

Then specify:

Spout opening.

Spout length.

Closure.

Filling equipment interface.

Any other critical dimensions.

Specify the Filling Method

Tell the supplier how product enters.

For example:

Gravity filling.

Conveyor.

Chute.

Filling head.

Other process equipment.

This helps ensure the top configuration matches the operation.

Specify Filling Equipment Dimensions

If the FIBC connects to equipment, measure the equipment.

Do not choose a filling spout because:

“That is what we normally buy.”

Design the opening around the actual interface.

Specify Required Filling Rate

If throughput matters, communicate it.

The bag should support production.

A technically correct FIBC that destroys filling cycle time may still be operationally wrong.

Specify Air Displacement Requirements

Product enters.

Air leaves.

This becomes particularly important with:

Powders.

Fast filling.

Coated fabric.

Liners.

Closed filling systems.

Tell the supplier about the actual filling process.

Specify Dust-Control Requirements During Filling

If dust is a concern, define it.

Possible design considerations can include:

Coating.

Seam construction.

Liner.

Top closure.

Filling connection.

Air management.

Do not expect “four-panel” to solve dust.

Specify the Bottom Construction Separately

The same rule applies below.

Four-panel tells you nothing about how product exits.

Specify the bottom.

How to Specify Flat Bottom on a Four-Panel FIBC Purchase Order

State:

Body Construction: Four-Panel

Bottom Construction: Flat Bottom / No Discharge Spout

Use this when controlled bottom discharge is unnecessary.

How to Specify Discharge Spout Bottom on a Four-Panel FIBC Purchase Order

State:

Body Construction: Four-Panel

Bottom Construction: Discharge Spout With Approved Closure

Then specify the required outlet geometry.

How to Specify Duffle Bottom on a Four-Panel FIBC Purchase Order

State:

Body Construction: Four-Panel

Bottom Construction: Duffle Bottom / Wide-Opening Discharge With Approved Closure

This may be useful where broader discharge is needed.

Specify the Discharge Method

How will product leave the FIBC?

Will it feed:

A hopper?

Mixer?

Conveyor?

Bin?

Process vessel?

Will product be removed another way?

The bottom needs to work with the actual process.

Specify the Required Discharge Rate

If unloading throughput matters, define the operational expectation.

A discharge outlet that is too restrictive can slow production.

One that is too large may release product faster than the receiving system can handle.

Specify Whether Partial Discharge Is Required

Does the operator empty the entire FIBC?

Or stop and restart product flow?

That can affect:

Bottom selection.

Closure.

Outlet design.

Receiving equipment.

Specify Product Flowability

Tell the supplier whether the product:

Flows freely.

Bridges.

Cakes.

Clumps.

Compacts.

Interlocks.

Flowability affects both filling and discharge.

Specify Particle Size

Particle size can influence:

Fabric.

Seams.

Dust.

Discharge outlet.

Liner.

Product flow.

Include it when relevant.

Specify Whether the Product Is Bulky or Irregular

Bulky and irregular materials can behave differently from powders or pellets.

They may require:

Broad filling access.

Broad discharge.

Different body dimensions.

Different fabric considerations.

Do not hide the actual material behavior.

Specify Whether the Product Is Abrasive

Abrasive products can create wear at:

Sidewalls.

Seams.

Bottom areas.

Discharge outlets.

Communicate abrasion requirements.

Specify Whether the Product Is Sharp or Angular

Sharp products can create:

Puncture concerns.

Wear.

Localized stress.

That information belongs in the application specification.

Specify Product Temperature When Relevant

If the product enters the FIBC at an elevated or unusual temperature, document it.

Material compatibility should be evaluated around actual conditions.

Specify Fabric Requirements

Do not simply write:

Polypropylene bag.

The supplier needs the approved fabric specification.

This may include requirements related to:

Fabric construction.

Weight.

Strength.

Coating.

UV considerations.

Other performance characteristics.

Specify Coated or Uncoated Fabric

State it.

Do not leave this open to interpretation.

Coated fabric can help with:

Fine-particle containment.

Resistance to moisture moving through woven fabric.

Uncoated fabric provides greater breathability.

Choose around the product.

Specify Seam Requirements

This matters with four-panel construction because the body contains multiple vertical seams.

Define any requirements for:

Strength.

Sift resistance.

Fine-particle containment.

Other application-specific performance.

Specify Sift-Resistant Seam Requirements When Needed

If you are packaging fine powder, communicate the containment requirement.

Do not assume a standard seam is appropriate for every product.

Specify Whether a Liner Is Required

If the product requires additional barrier performance, state the liner requirement separately.

Possible reasons include:

Moisture sensitivity.

Fine particles.

Contamination control.

Food-contact requirements.

Chemical compatibility.

Product protection.

Specify Loose-Insertion vs Form-Fit Liner

Do not write only:

With liner.

What liner?

Loose insertion?

Form fit?

Other approved configuration?

Specify it.

Specify Liner Thickness and Material When Required

If liner material or thickness is critical to the application, include it in the controlled specification.

Do not let it change silently from order to order.

Specify How the Liner Interfaces With the Top

If a filling spout is used, determine how the liner connects or aligns with the filling system.

The outer FIBC and liner need to function together.

Specify How the Liner Interfaces With the Bottom

Same thing on discharge.

If product exits through a discharge spout, the liner needs compatible discharge geometry.

Specify Moisture Requirements

Do not simply write:

Waterproof.

Define the actual requirement.

Consider:

Coating.

Liner.

Seams.

Top closure.

Bottom closure.

Storage.

Handling.

Nationwide transportation.

Specify Dust Requirements

If product loss or airborne dust is important, communicate it.

Fine powders may require a more controlled containment system than coarse pellets.

Specify Contamination Requirements

If cleanliness matters, define:

Product-contact requirements.

Fabric.

Liner.

Closures.

Manufacturing requirements.

Handling.

Packaging.

Do not assume four-panel construction tells the supplier any of this.

Specify Static Requirements When Applicable

Electrostatic requirements are separate from four-panel construction.

If the product or operating environment creates static concerns, specify the required FIBC classification and applicable conditions.

Specify Lift Loop Configuration

The bag needs to be handled.

Specify:

Loop style.

Loop location.

Loop dimensions.

Equipment compatibility.

Specify Lift Loop Length

Loop length can affect:

Forklift access.

Filling equipment.

Discharge equipment.

Overall hanging height.

Operator handling.

Control it when necessary.

Specify Overall Hanging Height

If the FIBC is suspended during filling or discharge, check the entire system.

Body.

Loops.

Top.

Bottom.

Equipment clearance.

Do not discover the bag is too tall after it arrives.

Call or Text us at 832.400.1394

Specify the Pallet

If the filled FIBC will be palletized, document the actual pallet configuration.

Then evaluate:

Filled footprint.

Overhang.

Height.

Handling.

Warehouse fit.

Transportation.

Specify Warehouse Requirements

If storage geometry matters, communicate it.

Does the FIBC need to fit a defined pallet position?

Is clearance limited?

Is warehouse cube expensive?

Does filled bulging create problems?

These details can influence the design.

Specify Nationwide Transportation Requirements

The FIBC needs to survive and function through the actual logistics chain.

Consider:

Payload.

Pallet configuration.

Filled dimensions.

Settling.

Vibration.

Handling.

Applicable weight constraints.

Truck or container loading.

If transportation geometry matters, put it into the design process.

Specify Whether the Shipment Cubes Out or Weighs Out

This is particularly important when evaluating filled dimensions.

If shipments run out of physical cube first, package geometry can have significant economic value.

If shipments hit applicable weight constraints first, tighter geometry may have less transportation value.

Know the actual constraint.

Specify Printing Requirements

Define required:

Company information.

Product identification.

Handling instructions.

Warnings.

Lot information.

Traceability.

Other markings.

Use controlled artwork when appropriate.

Specify Printing Location

With four distinct side panels, printing location should not be assumed.

Identify which panels receive printing and how artwork should be oriented.

Specify Empty-Bag Packing Requirements

How should empty FIBCs arrive?

Folded?

Baled?

Palletized?

Liners preinstalled?

Specific orientation?

Packing can affect plant efficiency.

Assign an Internal Item Number

Give the approved FIBC a controlled identity.

For example:

FIBC Item FP-210 — Rev. D

Now purchasing can order an exact design.

That is much safer than:

Four-panel bag we bought before.

Use Revision Control

If anything changes, update the controlled revision.

That includes:

Fabric.

Top.

Bottom.

Seams.

Liner.

Loops.

Dimensions.

Printing.

SWL.

Other critical construction details.

Do Not Use “Same as Last Time”

That phrase eventually creates trouble.

Which last time?

Which revision?

Which supplier?

Which liner?

Which seam?

Reference the approved item number and specification revision.

Do Not Let Changes Live Only in Email

Operations says:

“Make the loops longer.”

Engineering says:

“Change the discharge outlet.”

Quality says:

“We need better sift resistance.”

Supplier says:

“No problem.”

Then nobody updates the specification.

Six months later purchasing orders the old design.

If a change matters, control it.

Do Not Order a Four-Panel FIBC From a Photograph

A photo can show:

General shape.

Color.

Loops.

Top.

Maybe the bottom.

It cannot reliably tell you:

Fabric specification.

SWL.

Safety factor.

Seam construction.

Liner.

Critical dimensions.

Tolerances.

Use a technical drawing.

How to Write a Four-Panel FIBC Purchase Order Description

A useful description might follow this structure:

FIBC — Four-Panel Body Construction / [Top Construction] / [Bottom Construction] / [Required SWL] / [Required Safety Factor] / [Coated or Uncoated] / [Liner Requirement] / [Lift Loop Configuration] / Per Approved Specification [Revision]

Then reference the controlled drawing.

Example Four-Panel FIBC Purchase Order Specification

A controlled specification might include:

Product: Approved dry bulk material
Bulk Density: Approved value or range
Target Payload: Approved fill weight
Body Construction: Four-Panel
Top Construction: Approved top style
Bottom Construction: Approved bottom style
SWL: Required Safe Working Load
Safety Factor: Required intended-use classification
Fabric: Woven polypropylene per specification
Coating: Coated or uncoated as required
Seams: Per approved construction
Liner: Approved configuration if required
Lift Loops: Approved style and dimensions
Empty Dimensions: Per drawing
Critical Filled Dimensions: Per specification
Tolerances: Per approved drawing
Pallet: Approved configuration
Filling Method: Approved process
Discharge Method: Approved process
Dust Requirements: As applicable
Moisture Requirements: As applicable
Static Requirements: As applicable
Printing: Per controlled artwork
Packing: Per approved requirement
Revision: Current approved revision

That gives purchasing something repeatable.

Example Open Top Four-Panel FIBC Purchase Order

Body Construction: Four-Panel

Top Construction: Full Open Top

Bottom Construction: Approved Bottom

SWL / Safety Factor / Fabric / Loops / Dimensions: Per Approved Specification

Simple.

Controlled.

Example Duffle Top Four-Panel FIBC Purchase Order

Body Construction: Four-Panel

Top Construction: Duffle Top With Approved Closure

Bottom Construction: Approved Bottom

Then reference the complete specification.

Example Filling Spout Four-Panel FIBC Purchase Order

Body Construction: Four-Panel

Top Construction: Filling Spout With Approved Opening, Length, and Closure

Bottom Construction: Approved Bottom

Now filling equipment compatibility is controlled.

Example Four-Panel FIBC With Discharge Spout Bottom

Body Construction: Four-Panel

Top Construction: Approved Top

Bottom Construction: Discharge Spout With Approved Opening, Length, and Closure

Then define the receiving equipment and discharge requirements.

Example Four-Panel FIBC With Duffle Bottom

Body Construction: Four-Panel

Top Construction: Approved Top

Bottom Construction: Duffle Bottom / Wide-Opening Discharge With Approved Closure

Then verify the actual product can discharge as intended.

Four-Panel FIBC Purchase Order Checklist

Before releasing the PO, confirm:

  1. Is four-panel body construction clearly specified?
  2. Is the approved technical drawing referenced?
  3. Is the product identified?
  4. Is bulk density documented?
  5. Is target payload documented?
  6. Is SWL specified?
  7. Is safety factor specified?
  8. Is top construction specified?
  9. Is bottom construction specified?
  10. Is filling method defined?
  11. Is discharge method defined?
  12. Is product flowability understood?
  13. Is particle size understood?
  14. Is abrasion understood?
  15. Are sharp or angular characteristics understood?
  16. Is fabric specified?
  17. Is coating specified?
  18. Are seam requirements specified?
  19. Are sift-resistance requirements defined if applicable?
  20. Is a liner required?
  21. Is liner style specified?
  22. Does the liner work with filling?
  23. Does the liner work with discharge?
  24. Are moisture requirements defined?
  25. Are dust requirements defined?
  26. Are contamination requirements defined?
  27. Are static requirements defined when applicable?
  28. Are lift loops specified?
  29. Is loop length specified when critical?
  30. Is overall hanging height acceptable?
  31. Are empty dimensions controlled?
  32. Are critical filled dimensions controlled?
  33. Are tolerances realistic?
  34. Is pallet compatibility defined?
  35. Is acceptable overhang understood?
  36. Are warehouse requirements understood?
  37. Are nationwide transportation requirements understood?
  38. Is printing controlled?
  39. Is packing controlled?
  40. Is the current revision referenced?

If those questions have answers, you are getting close to a real specification.

Common Mistakes When Specifying Four-Panel Construction

Common mistakes include:

Writing only “four-panel bag.”

Writing only “heavy-duty four-panel.”

Assuming four-panel means baffle.

Assuming four-panel means perfectly square when filled.

Assuming four-panel automatically means stronger.

Ignoring the actual product.

Ignoring bulk density.

Ignoring target payload.

Ignoring SWL.

Ignoring safety factor.

Ignoring top construction.

Ignoring bottom construction.

Ignoring seam requirements.

Ignoring coating.

Ignoring liners.

Ignoring filling equipment.

Ignoring discharge equipment.

Ignoring air displacement.

Ignoring dust.

Ignoring moisture.

Ignoring static requirements.

Ignoring lift loops.

Ignoring hanging height.

Ignoring filled dimensions.

Ignoring pallet overhang.

Ignoring warehouse requirements.

Ignoring nationwide transportation.

Ordering from a photograph.

Using “same as last time.”

Allowing changes to exist only in emails.

Failing to control revisions.

What Purchasing Should Ask Operations

Ask:

How is the bag filled?

How long does filling take?

Does the current top work?

Does product dust?

Does product leak or sift?

Does the bag bulge?

Does it fit the pallet?

Does the liner move?

How is the bag discharged?

Does product bridge?

How much product remains after discharge?

Operations knows what happens in real life.

What Purchasing Should Ask Warehouse Teams

Ask:

Does the current filled FIBC fit the pallet?

How much overhang exists?

Does it interfere with adjacent loads?

Does it remain stable?

Do loops remain accessible?

Does the filled geometry create wasted warehouse space?

That information can influence the specification.

What Purchasing Should Ask Logistics Teams

Ask:

What filled dimensions matter?

How are the FIBCs loaded?

Does the shipment cube out?

Does it weigh out?

How much product moves per shipment?

Does bulging affect load planning?

How does the bag behave after transportation?

The packaging should work with the logistics system.

What Purchasing Should Ask Engineering

Ask:

Why is four-panel construction required?

What dimensions are critical?

What seam construction is required?

What fabric is required?

What top and bottom configuration should be used?

Is a liner required?

What SWL and safety factor are required?

What tolerances actually matter?

Engineering should define performance.

Purchasing should control it.

Why Samples Matter Before Large Four-Panel FIBC Orders

Do not approve only the empty bag.

Fill it.

With the real product.

At the real target payload.

Using the real filling equipment.

Then evaluate:

Filling time.

Air displacement.

Dust.

Seams.

Liner.

Filled dimensions.

Pallet fit.

Overhang.

Loops.

Handling.

Settling.

Discharge.

Residual product.

That tells you whether the specification actually works.

How to Approve a Four-Panel FIBC Specification

Approval should involve the complete process.

Fill the FIBC.

Measure it.

Handle it.

Store it.

Move it.

Discharge it.

Then document the approved design.

Assign:

Item number.

Drawing.

Revision.

Approved sample when appropriate.

Now future purchase orders can reference a controlled standard.

How Detailed Should the Purchase Order Be?

The PO itself does not need to contain every manufacturing detail.

It needs to point unambiguously to the document that does.

For example:

FIBC Item FP-210, Rev. D — Four-Panel Construction Per Approved Drawing and Specification

That can be enough if the referenced documents contain the complete controlled design.

Why Standardizing Four-Panel FIBC Specifications Saves Money

Standardization can improve:

Quote accuracy.

Supplier comparison.

Receiving inspection.

Quality consistency.

Inventory management.

Warehouse planning.

Production efficiency.

Repeat ordering.

Troubleshooting.

It also reduces the expensive sentence:

“That isn’t what we ordered last time.”

How to Compare Four-Panel FIBC Quotes Correctly

Before comparing price, confirm each quote is based on the same:

Product.

Bulk density.

Payload.

Body construction.

SWL.

Safety factor.

Top.

Bottom.

Fabric.

Coating.

Seams.

Liner.

Loops.

Dimensions.

Tolerances.

Printing.

Packing.

Performance requirements.

Otherwise you may be comparing different bags that happen to share the words:

Four-panel FIBC.

The Best Way to Specify Four-Panel Construction on an FIBC Purchase Order

Start with the product.

Not the bag.

What material is going inside?

What is its bulk density?

How does it flow?

Is it dusty?

Abrasive?

Sharp?

Moisture sensitive?

Static sensitive?

What is the target payload?

Then define the process.

How does product enter?

What equipment fills the FIBC?

How quickly?

How does air escape?

How does product leave?

Does it feed a hopper?

Conveyor?

Mixer?

Does the entire load discharge at once?

Now define the body.

Four-panel.

Then define the top.

Open.

Duffle.

Filling spout.

Then the bottom.

Flat.

Spout.

Duffle.

Then specify:

SWL.

Safety factor.

Fabric.

Coating.

Seams.

Liner.

Loops.

Dimensions.

Tolerances.

Pallet.

Filled footprint.

Printing.

Packing.

Revision.

Then test it.

Use the actual product.

Use the actual target payload.

Use the actual filling system.

Use the actual pallet.

Measure the filled bag.

Let it settle.

Measure again.

Move it.

Store it.

Put it through representative nationwide transportation conditions.

Then discharge it through the actual receiving process.

Check:

Filling time.

Dust.

Air displacement.

Filled geometry.

Pallet overhang.

Handling.

Liner behavior.

Discharge time.

Residual product.

Product loss.

If it works, lock the design.

Assign the item number.

Approve the drawing.

Control the revision.

Now purchasing can order the same FIBC repeatedly.

Because “four-panel” should identify the body construction—not force everybody else to guess the rest of the bag.